Module 2: Emergency Planning Notification
 
Return
 
Steps 9 and 10
     
  
 
  
    One-Time Reporting Requirements    
     
  
 
  
    This section of Module 2 describes one-time reporting requirements, unless updates are required (see Step 14).    
     
     
    Step 11
 
Notify the State Emergency Response Commission (SERC) that the facility has present an amount of EHS that is greater than or equal to its TPQ. This notification can be accomplished through a letter.
 
An example of a letter to the SERC is provided. PDF File - SERC Notification Letter
   
   
arrow
   
     
    Step 12
 
Designate a person at the facility to be the facility emergency planning coordinator. This person will act as a liaison with the Local Emergency Planning Committee (LEPC).
   
   
arrow
   
     
    Step 13
 
Notify the LEPC that the facility has present an amount of EHS that is greater than or equal to its TPQ and provide the LEPC with the identity of the facility emergency planning coordinator. Thsi notification can be accomplished through a letter.
 
An example of a letter to the LEPC is provided. PDF File - LEPC Notification Letter
   
   
arrow
   
     
    Step 14
 
At this point, the facility's Emergency Planning Notification responsibilities are complete until the LEPC requests additional information or changes occur at the facility which affect emergency planning.
   
     
    continue
 
Module 2, Steps 15 and 16
   
 
Go To: Module 2 Index or EPCRA's Main Index or EPCRA Table of Contents